Lighting BOQ & Tender Preparation — Quantity Estimation for Projects

How to prepare accurate Bills of Quantities and professional tender documents for lighting projects.

6 min LEDWORLD Technical Team 17 views
Lighting BOQ & Tender Preparation — Quantity Estimation for Projects

BOQ Structure for Lighting

A professional lighting Bill of Quantities (BOQ) itemizes every component needed for procurement and installation. Typical BOQ sections: 1. Luminaires: Each fixture type listed with tag, description, quantity, unit rate, and total. 2. Lamps/LED modules: If separately supplied (rare for modern LED, but common for retrofit projects). 3. Control gear: Drivers, ballasts, and transformers if not integral to the luminaire. 4. Controls: DALI controllers, sensors, switches, panels, gateways, software licenses. 5. Wiring accessories: Cable, conduit, junction boxes, fire barriers for recessed fittings. 6. Installation: Labour for each fixture type (rates vary by mounting type: recessed, surface, suspended, in-ground). 7. Commissioning: Programming, aiming, scene setting, photometric verification. 8. Spares: Typically 5-10% spare luminaires and 10% spare drivers/modules.

BOQ Example — Office Floor

01234
1.1DL-01Recessed LED Downlight 15W 4000K DALI86Nr
1.2LP-01Recessed LED Panel 600x600 40W 4000K DALI42Nr
1.3LL-01Suspended Linear LED 1200mm 35W Direct/Indirect28Nr
1.4WW-01LED Wall Washer 12W Adjustable16Nr
2.1CTRL-01DALI-2 Gateway 64-device4Nr
2.2CTRL-02PIR Occupancy Sensor DALI24Nr
2.3CTRL-03Daylight Photosensor DALI8Nr
2.4CTRL-044-Button Scene Panel12Nr
3.1—Installation (recessed fixtures)144Nr
3.2—Installation (suspended fixtures)28Nr
4.1—Commissioning and scene programming1LS
5.1—Spare luminaires (5%)9Nr
5.2—Spare drivers (10%)18Nr

Tender Evaluation Criteria

When evaluating lighting tenders, use a weighted scoring system: • Technical compliance (40%): Do proposed products meet all specification requirements? Check IES files, TM-30 data, flicker reports, warranty, IP/IK ratings. • Price (30%): Total cost including supply, delivery, installation, commissioning, and spares. • Manufacturer quality (15%): Track record, local support, warranty infrastructure, reference projects in the region. • Delivery timeline (10%): Can the manufacturer deliver within the project schedule? Lead times for custom finishes or non-standard items. • Sustainability (5%): Environmental certifications, recycled content, recyclability, energy labeling. Never select on price alone — the cheapest tender in lighting almost always results in substituted products, poor quality, commissioning issues, and premature failures.

Tender Preparation Checklist

Prepare detailed luminaire schedule with all performance requirements
Create BOQ with itemized quantities for fixtures, controls, installation, and commissioning
Include IES file and TM-30 data submission requirements for all proposed products
Define evaluation criteria with weightings before issuing tender
Require physical samples/mock-ups for feature luminaires before approval
Include commissioning scope: DALI addressing, scene programming, photometric verification
Specify spare quantities: typically 5% luminaires, 10% drivers/modules
Allow minimum 3 weeks for tender preparation and questions
Conduct technical evaluation before opening commercial proposals

Frequently Asked Questions

BOQtenderprocurementquantitiespricingevaluationspecification

Planning a procurement lighting project?

LEDWORLD has completed 6,000+ lighting projects across the UAE and GCC. Our team can handle everything from lighting design to supply and installation.

Related solutions

Discuss your project →

Discuss your lighting requirements

We use cookies to enhance your experience.Privacy Policy